Annex A (informative) — Metric Examples

A.1 Important Note

The metrics and their targets in table below are ONLY EXAMPLES.

Each organization or plant will determine:

  • Its own metrics
  • Its own targets

Actual targets could be different depending upon factors such as:

Process type:

  • Continuous vs. batch
  • Chemical vs. refining
  • Simple vs. complex

Operator skill:

  • Experienced vs. new
  • Training level
  • Team capability

HMI:

  • System capabilities
  • Display quality
  • Usability

Operating environment:

  • 24/7 vs. dayshift only
  • Staffing levels
  • Support available

Types of automated procedures:

  • Startup/shutdown
  • Normal operation
  • Emergency response

Significance:

  • Safety-critical
  • Production-critical
  • Non-critical

Customize metrics to YOUR situation!

A.2 Metric Table

Below is comprehensive table with 7 example metrics:

No. Description Target Reason for Metric Potential Corrective Action
1 Percentage of times operators manually perform a procedure instead of using an available automated procedure 0% Ensure the business justification for the procedure is met Analyze why the procedure is not being used as expected
2 The number of operator control interactions performed by the operator in a fixed period (See Note below table) No more than an average of x interactions in a y period

No more than a peak of z interactions in a y period
Manage the operator workload Increase automation or staffing
3 Number of times an operator had to intervene (deviate, override, abort, change a step…) when an automated procedure was run or per a period 0 Identifies problems with an automated procedure

Identifies improper operator training

Identifies instrumentation or process equipment problems
Redesign the procedure

Improve operator training

Correct or replace instrumentation or process equipment
4 The number of times support from engineering is required during execution per period 0 Identifies problems with an automated procedure

Identifies improper operator training

Identifies instrumentation or process equipment problems
Redesign the procedure

Improve operator training

Correct or replace instrumentation or process equipment
5 The number of times an automated procedure experienced an abnormal end of execution per period 0 Identifies problems with an automated procedure Redesign the procedure
6 Average, maximum, minimum, and standard deviation of the duration of an entire automated procedure, tasks, or steps in an automated procedure Procedure dependent Identifies opportunities for improving plant operation Investigate procedure, process and equipment improvement opportunities
7 Product quality and yield measures Product and procedure dependent Identifies opportunities for improving plant operation

Identify shift differentials if possible

Identifies improper operator training

Identifies instrumentation or process equipment problems
Investigate procedure, process and equipment improvement opportunities

A.3 Detailed Metric Explanations

A.3.1 Metric 1: Manual Operation Instead of Automation

What it measures:

Percentage of times operators manually perform procedure instead of using available automated procedure.

Example:

  • Automated startup procedure available
  • Should be used 100% of time
  • Actual: Used 85% of time
  • Metric: 15% manual operation (problem!)

Target: 0%

Why 0% target?

  • Procedure was justified based on benefits
  • Benefits only realized if used
  • Manual operation = wasted investment

Reason for metric:

Ensure business justification met:

  • ROI requires utilization
  • Benefits require usage
  • Investment wasted if not used

Potential corrective action:

Analyze why procedure not being used:

Possible reasons:

  • Procedure doesn’t work well
  • Operators don’t trust it
  • Manual method faster
  • Training inadequate
  • Inconvenient to use
  • Poor usability

Actions:

  • Interview operators
  • Observe usage
  • Identify barriers
  • Fix problems
  • Improve usability
  • Better training

Goal: 100% automated procedure usage!

A.3.2 Metric 2: Operator Control Interactions

What it measures:

Number of operator control interactions performed by operator in fixed period.

See Note below table for definition of “control interactions.”

Target:

Two-part target:

Average:

No more than average of x interactions in y period

Peak:

No more than peak of z interactions in y period

Example targets:

  • Average: ≤ 30 interactions per hour
  • Peak: ≤ 50 interactions per hour

Why two targets?

Average alone misleading:

  • Could be 10/hour for 3 hours, then 100/hour for 1 hour
  • Average: 32.5/hour (seems OK)
  • But peak 100/hour = overload!

Peak alone misleading:

  • Could be 5/hour for 3 hours, then 50/hour for 1 hour
  • Peak: 50/hour (at target)
  • But mostly underutilized

Both needed for complete picture!

Reason for metric:

Manage operator workload:

  • Too many interactions = overload
  • Operator error increases
  • Safety risk
  • Fatigue

Potential corrective action:

Increase automation:

  • Automate more tasks
  • Reduce manual interactions
  • Optimize procedures

OR increase staffing:

  • More operators
  • Distribute workload
  • Reduce individual loading

High interaction rate = automation opportunity!

A.3.3 Metric 3: Operator Interventions

What it measures:

Number of times operator had to intervene:

  • Deviate from procedure
  • Override automation
  • Abort procedure
  • Change a step
  • Manual action during automation

When:

  • Automated procedure was run
  • OR per period (e.g., per month)

Target: 0

Why 0% target?

  • Intervention means automation not working
  • Should run without intervention
  • Interventions indicate problems

Reason for metric (3 possible causes):

Cause 1: Problems with automated procedure

  • Logic errors
  • Design flaws
  • Not handling conditions
  • Inadequate exception handling

Cause 2: Improper operator training

  • Don’t understand procedure
  • Intervene unnecessarily
  • Lack confidence
  • Poor training

Cause 3: Instrumentation or equipment problems

  • Sensors failing
  • Valves sticking
  • Equipment degraded
  • Maintenance needed

Potential corrective action:

Redesign procedure:

  • Fix logic errors
  • Improve exception handling
  • Better design

Improve operator training:

  • Better understanding
  • When to intervene
  • When not to intervene
  • Confidence building

Correct or replace instrumentation/equipment:

  • Fix sensors
  • Repair valves
  • Replace degraded equipment
  • Preventive maintenance

Root cause analysis determines which action!

A.3.4 Metric 4: Engineering Support Required

What it measures:

Number of times support from engineering required during execution per period.

Example:

  • Startup procedure executing
  • Problem occurs
  • Operator calls engineer
  • Engineer must help

Target: 0

Why 0% target?

  • Operators should be able to execute without engineering
  • Engineering support during execution = problem
  • Not scalable or sustainable

Reason for metric (same 3 causes as Metric 3):

Cause 1: Problems with procedure

Cause 2: Improper training

Cause 3: Equipment problems

Potential corrective action (same as Metric 3):

  • Redesign procedure
  • Improve training
  • Fix equipment

Well-designed procedure + trained operators = no engineering support needed!

A.3.5 Metric 5: Abnormal End of Execution

What it measures:

Number of times automated procedure experienced abnormal end of execution per period.

What is “abnormal end”?

Normal end:

  • Procedure completes successfully
  • All steps executed
  • Objectives achieved
  • Clean completion

Abnormal end:

  • Procedure aborts
  • Error termination
  • Timeout failure
  • Exception not handled
  • Crash

Target: 0

Why 0% target?

  • Every execution should complete normally
  • Abnormal ends = bugs or design flaws
  • Not acceptable

Reason for metric:

Identifies problems with automated procedure:

  • Software bugs
  • Logic errors
  • Unhandled exceptions
  • Design flaws
  • Inadequate error handling

Potential corrective action:

Redesign procedure:

  • Fix bugs
  • Improve logic
  • Better exception handling
  • More robust design
  • Comprehensive testing

This metric = quality indicator!

A.3.6 Metric 6: Duration Statistics

What it measures:

Duration statistics of automated execution:

Average:

Mean time to complete

Maximum:

Longest execution time

Minimum:

Shortest execution time

Standard deviation:

Variation in execution time

For:

  • Entire automated procedure
  • Individual tasks
  • Individual steps

Target: Procedure dependent

Why procedure dependent?

  • Each procedure different
  • Different processes
  • Different equipment
  • Different objectives

Must establish baseline:

  • Measure initial performance
  • Set targets based on baseline
  • Track changes over time

Example baseline:

Distillation startup procedure:

  • Average: 4.0 hours
  • Maximum: 4.5 hours
  • Minimum: 3.7 hours
  • Standard deviation: 0.15 hours

Targets could be:

  • Average: 3.5 hours (improvement goal)
  • Maximum: 4.0 hours (control variability)
  • Standard deviation: 0.10 hours (consistency goal)

Reason for metric:

Identifies opportunities for improving plant operation:

Long average:

  • Process slow
  • Automation inefficient
  • Equipment problems
  • Optimization opportunity

High maximum:

  • Inconsistent performance
  • Occasional problems
  • Investigation needed

High standard deviation:

  • High variability
  • Inconsistent execution
  • Different operators
  • Different conditions
  • Need standardization

Potential corrective action:

Investigate improvement opportunities:

  • Procedure optimization
  • Process improvements
  • Equipment upgrades
  • Better control strategies

This metric = optimization guide!

A.3.7 Metric 7: Product Quality and Yield

What it measures:

Product quality measures:

  • Specification compliance
  • Purity
  • Grade
  • Customer satisfaction
  • Rework rate

Yield measures:

  • Production quantity
  • Raw material utilization
  • Waste/byproducts
  • Efficiency

Target: Product and procedure dependent

Why product/procedure dependent?

  • Different products
  • Different specifications
  • Different targets
  • Different markets

Must establish baseline and targets.

Example targets:

  • Quality: 99% within specification
  • First-pass yield: >98%
  • Rework rate: <1%
  • Production rate: 100 ± 5 tons/day

Reason for metric (4 possible insights):

Insight 1: Opportunities for improving operation

  • Quality can be improved
  • Yield can be increased
  • More value available

Insight 2: Identify shift differentials

  • Day shift: 99.5% quality
  • Night shift: 98.0% quality
  • Different performance!

Why shift differentials?

  • Training differences
  • Experience levels
  • Operator skill
  • Procedure usage

Insight 3: Improper operator training

  • Quality varies by operator
  • Some better than others
  • Training needed

Insight 4: Instrumentation or equipment problems

  • Quality degrading over time
  • Equipment wearing
  • Sensors drifting
  • Maintenance needed

Potential corrective action:

Investigate improvement opportunities:

  • Procedure optimization
  • Process improvements
  • Equipment upgrades
  • Better control

This metric = business value indicator!

A.4 Note on Operator Control Actions

Operator control actions are one component of control room operator loading.

What are operator control actions?

Actions taken by control room operator:

  • Mode changes
  • Setpoint changes
  • Opening/closing a valve
  • Starting/stopping a pump
  • Parameter adjustments

Other loading components may include:

  • Display interactions
  • Alarm acknowledgment
  • Radio communications
  • Field actions (in some cases)

Why measure control actions?

Analysis of operator control action rates is good indicator of:

Overall health of automated procedures:

  • High rate = procedure requires too much interaction
  • Low rate = procedure highly automated
  • Trending = performance over time

Risk of operator error:

Any procedure requiring high level of operator interaction in fixed period:

Increases potential of operator error.

Why?

  • Workload overload
  • Attention diluted
  • Fatigue
  • Mistakes increase

Important analysis practices:

Interview operators:

  • Understand their experience
  • Get qualitative feedback
  • Context for metrics

Use interview information:

  • Understand effects of metrics
  • Identify causes
  • Guide corrective actions

Peak vs. Average:

Both should be taken into account.

Why both?

Either measurement individually could be misleading:

Example misleading average:

  • Hour 1: 10 actions
  • Hour 2: 10 actions
  • Hour 3: 10 actions
  • Hour 4: 100 actions
  • Average: 32.5/hour (seems OK)
  • But Hour 4 = overload!

Example misleading peak:

  • Hour 1: 5 actions
  • Hour 2: 5 actions
  • Hour 3: 5 actions
  • Hour 4: 50 actions
  • Peak: 50/hour (at limit)
  • But mostly underutilized

The danger:

Any period producing more operator control interactions than can be handled:

Increases likelihood of human error:

Even if average for that interval seems acceptable!

Short overload periods dangerous!

Monitor both: Average AND peak!